LINCOLN COMMUNITY SCHOOL - SOLAR PROJECT

PROJECT BRIEF 
On 25th June, 2018, PPA Ltd commenced installation of a 247kWp Grid-Tied Solar PV power at the Lincoln Community School. The project per work schedule is to be completed and commissioned by the 21st January, 2019. The system consists of the mounting & installation of solar modules on both flat roofs & rooftops which demand very meticulous adherence to high safety standards to avert injury & damage to equipment.

The system was designed with an aim to supplement 30% of the school’s energy demand on utility, thereby reducing their energy bill cost by close to 30%. With solar PV systems being scalable, we are in talks with the management of the school to consider avenues to increase & expand the capacity of the system.